QantasLink A320 Wifi Updates
Summary: The Network Aviation / QantasLink A320 2026 in-flight connectivity (wifi) retrofit program has reached a
confirmed 95% fleet completion rate (18 of 19 airframes), with the last aircraft suspected to be undergoing modification at Perth Airport (YPPH) currently. The A319s are presumed to be next.
Tracking this retrofit program since the start has relied heavily on monitoring downtime. As the workhorses of the WA fleet, these A320s are constantly in the air flying regional and charter routes. Because they typically fly every day for weeks at a time, any sudden, multi-day pause in an aircraft's schedule is a strong indicator that it has entered the Perth hangars.
However, the hangar downtime alone doesn't guarantee a completed installation. Whilst generally not the case, they could be down for any reason such as inspections, delays, damage, failure etc.
So, to fully verify the modification, it ultimately comes down to catching a visual of the aircraft - finding the new radome "hump" sitting on the roof, indicating the downtime was indeed for wifi. Finding this proof requires a bit of hunting... livestreams, webcams, and planespotter photos across Instagram and TikTok, any social media page you can think of to find the humps along with the registrations. Because the medium-profile radome used by Qantas is so prominent (its only benefit over a low-profile lol), seeing it confirms the aircraft has successfully cleared its modification slot.
Once that exterior radome is spotted, it's almost certain the plane has wifi. As demonstrated during the 787 rollout, if that hump is present, the WiFi is highly likely to be operational.
| Registration | Status | Suspected MRO Arrival | Suspected MRO Return | Downtime (Days) | Radome Spotted |
| VH-UVT | Completed | 02/07/2026 | 13/07/2026 | 11 | Yes |
| VH-VQM | Completed | 13/07/2026 | 22/07/2026 | 9 | Yes |
| VH-VQE | Completed | 17/07/2026 | 29/07/2026 | 12 | Yes |
| VH-VQU | Completed | 17/07/2026 | 27/07/2026 | 10 | Yes |
| VH-VQF | Completed | 27/07/2026 | 07/08/2026 | 11 | Yes |
| VH-VQR | Completed | 08/08/2026 | 13/08/2026 | 5 | Yes |
| VH-VQZ | Completed | 13/08/2026 | 17/08/2026 | 4 | Yes |
| VH-JQL | Completed | 14/08/2026 | 24/08/2026 | 10 | Yes |
| VH-JQX | Completed | 20/08/2026 | 25/08/2026 | 5 | Yes |
| VH-VQP | Completed | 20/08/2026 | 24/08/2026 | 4 | Yes |
| VH-VQW | Completed | 24/08/2026 | 31/08/2026 | 7 | Yes |
| VH-VQS | Completed | 27/08/2026 | 02/09/2026 | 6 | Yes |
| VH-VQQ | Completed | 01/09/2026 | 07/09/2026 | 6 | Yes |
| VH-JQG | Completed | 04/09/2026 | 10/09/2026 | 6 | Yes |
| VH-UVQ | Completed | 09/09/2026 | 16/09/2026 | 7 | Yes |
| VH-UVP | Completed | 14/09/2026 | 19/09/2026 | 5 | Yes |
| VH-UVK | Completed | 17/09/2026 | 22/09/2026 | 5 | Yes |
| VH-UVO | Completed | 21/09/2026 | 27/09/2026 | 6 | Yes |
| VH-UVJ | In Progress - Suspected | 25/09/2026 | -- | -- | Last remaining unmodified airframe |
Data
When the retrofit program launched in early July, the initial installations required hangar time of above 9 days. However as the rollout progressed, it was evident that they may have optimised the program. By August and into September, turnaround times were reduced by more than half, with VQP and VQZ being completed in an impressive 4 days.
Completing 18 installations in under three months likely required the use of multiple hangar bays simultaneously. The data shows concurrent arrivals, such as VH-VQE and VH-VQU both arriving on July 17th, followed by VH-JQX and VH-VQP on August 20th. Operating these parallel modification lines was likely to minimise disruptions to the schedule, and increase the pace of the program.
Installations
Every installation in this rollout has been completed locally at the hangars at Perth Airport (YPPH). Rather than ferrying aircraft out to the eastern states or overseas facilities (like Hong Kong for the 787s), the entire retrofit program has been managed completely in WA.
This also clears up the mystery around VQW. There was initial suspicion that it might have received the Wi-Fi upgrade while over in Singapore (XSP) alongside its heavy maintenance. As it turns out, it skipped the overseas install and simply had it completed in Perth.
Performance
I've taken a few flights on these newly modified A320s, and the speed sits right in line with standard domestic Qantas Wi-Fi. They generally hover around 20 Mbps down and 8 Mbps up. It is nothing terrible and nothing amazing, but it works perfectly fine for social media and general browsing. They show up as ''No wifi available'' on the Qantas app as usual though, like we saw for the 787 fleet. As aircraft swaps for flights using the A320s in WA are common, it is much better for the WiFi to be an unexpected bonus than a reason to complain if a connected frame gets swapped for an unmodified one. Even with all of the A320s connected, it is likely Qantas will keep it this way for a few weeks.
Seats and Program Splitting
When Qantas officially announced this upgrade for the fleet back in January, the
press release bundled the Wi-Fi rollout with a major cabin refresh, promising all-new seats equipped with USB A/C charging ports and portable device holders. However, on all of the flights I have been on I am met with the same old Jetstar seats. In addition to this I haven't seen any mentions/photos of them being upgraded.
Looking at the data and those four-day turnarounds, it is safe to assume the overall program has been split into two phases to keep the fleet flying. By splitting the radome installation from a full interior teardown, they could prioritize getting the hardware fitted and the Wi-Fi switched on without grounding each aircraft for weeks at a time. It is likely the physical seat upgrades have been deferred until each airframe rotates through its scheduled heavy maintenance checks. - A note on this, the new seats could have been installed on VH-VQW when it went to Singapore XSP for a month. However not sure.
Whats Next
With VH-UVJ currently offline as the presumed final airframe, this A320 Wi-Fi program is on the
verge of 100% completion. The sheer speed of these installations raises interesting questions for the rest of the fleet. I will keep an eye on the smaller fleet of 9 A319s, and give any updates, I assume they are next.